Status as of 22 October 2026. We will update this post when the Department of Public Utilities decides on the 2027–2030 programs.
The current utility EV charging programs in Massachusetts end on 31 December 2026. That date comes from the Department of Public Utilities (DPU) itself: both Eversource’s and National Grid’s current programs “will conclude on December 31, 2026.” The programs for 2027–2030 have been filed but, as of 22 October 2026, not approved.
If your condo board or building has been talking about chargers “next spring,” the window for 2026 terms is now a matter of weeks. Here are the dates that still matter, what the utilities say about 2027, and what to do this month.
The dates
| Date | Utility | What it is |
|---|---|---|
| 1 October 2026 (passed) | Eversource | Recommended date to apply for business and multi-unit rebates; later applications reviewed as time permits |
| 1 November 2026 | Eversource | Last day to submit a home charger rebate application, complete and with Managed Charging enrollment |
| 31 December 2026 | Eversource | Fully executed Letter of Agreement returned |
| 31 December 2026 | National Grid | Signed Pre-Approval Offer Letter returned, for multi-unit dwelling and public/workplace incentives |
| 31 December 2026 | Both | Current programs end |
For a board starting today, a 2026 approval is possible but not likely. Treat it as a long shot, and prepare for 2027 at the same time.
Eversource: 1 November for home chargers and small buildings
Eversource’s residential rebate page says applications must be complete and accurate, with “Managed Charging enrollment by November 1, 2026.”
This rebate covers a charger used by one household, or a charger shared by households in a building of two to four units. Larger buildings use Eversource’s multi-unit program (below). A small two-to-four-unit association sharing a charger is also working to 1 November.
Eversource says the rebates mainly offset wiring work for a Level 2 smart charger; income-eligible customers may also get up to 100% off the charger itself. Managed Charging pays a $10 monthly reward. Installations completed after 1 November “may apply for rebates if the program is available in 2027.”
Eversource: shared garages in buildings with five or more units
The DPU’s summary of Eversource’s 2023–2026 program describes its multi-unit offer as serving “multi-unit dwelling sites with five or more units.” Eversource’s business EV page says 2026 is the final year of the current program. It asked for applications by 1 October 2026; later ones “will be accepted but will be reviewed as processing time permits.” Funding is reserved only when a Letter of Agreement is fully executed and returned by 31 December 2026, and letters received after that “will not be accepted.” Its multi-unit offer covers Level 2 charging.
Eversource’s own page says multi-unit and fleet funding is available through 2026, “subject to change based on demand,” and applications are approved first-come, first-served.
National Grid: 31 December for multi-unit buildings
National Grid’s Multi-Unit Dwelling page is headed “Final Year for Current Multi-Unit Dwelling Program.” The key points:
- The program is for properties with 5 or more residential units, where chargers are wired behind a shared utility meter. It offers “up to 100% funding of the electrical infrastructure costs and additional rebates on charging station equipment costs.”
- The program “is nearing the end of its available budget.” Applications are still accepted “as funding becomes available,” and submitting one “does not guarantee funding.”
- You must return the signed Pre-Approval Offer Letter “no later than December 31, 2026.” Letters received after that date “will not be accepted.” The project itself can be finished and activated later, as the letter specifies.
- Properties with 20 or more units can get an EV-Ready Site Plan, with “up to 100% of the cost of the report” funded.
- If the chargers would be wired to residents’ own utility accounts, the project is not eligible for this program. Each installation may qualify for the residential program instead.
National Grid also says not to buy equipment or start construction before approval.
Public and workplace sites
National Grid’s Public/Workplace Programs page carries the same notice for public and workplace charging: the program “is nearing the end of its available budget,” and the signed Pre-Approval Offer Letter must be returned “no later than December 31, 2026.”
A state program to check
The state also runs its own incentive. MassDEP’s MassEVIP Multi-Unit Dwelling & Educational Campus Charging program is open to multi-unit dwellings with five or more residential units. It funds up to 60 percent of hardware and installation costs, to a maximum of $50,000 per street address, and accepts applications first-come, first-served until the funding is spent. Check it alongside your utility’s program.
What happens in 2027
Both utilities filed new programs with the DPU on 30 December 2025, and the DPU set a joint public hearing for 11 February 2026:
| Eversource | National Grid | |
|---|---|---|
| Docket | D.P.U. 25-188 (Phase III) | D.P.U. 25-189 (Phase IV) |
| Years | 2027–2030 | 2027–2030 |
| Proposed total | $165.6 million | $193.7 million |
| Commercial segment | $83 million | $101.9 million |
| Residential segment | $44 million | $42.3 million |
| Managed charging | $4.4 million | $23.6 million |
| Supporting elements | $34.2 million | $25.8 million |
These are proposals, not approved budgets. On its own pages, each utility says the decision is still pending. Eversource: “We’re awaiting the 2027 program approval from the Department of Public Utilities,” and “Modifications to program structure and incentives are expected for 2027.” National Grid: its Phase IV proposal “is currently under review,” and “program offerings, eligibility requirements, incentive levels, and timing will be confirmed following a Department order.”
What this means for you: if your building waits for 2027, you will apply under rules nobody has seen yet. They may be better or worse for your project. And there may be a gap between the end of the old programs and the start of the new ones. That last point is our reading, not something the utilities have said.
What the program rules ask of your equipment
Two rules on National Grid’s page are worth knowing before you choose chargers or software:
- Hardware. Since 1 January 2025, Level 2 and DC fast chargers must be listed on the Massachusetts tab of the EPRI Vetted Products List.
- Network. Networking is not required in the multi-unit program. If you choose networked chargers, you may be eligible for a networking stipend, and the network must be on National Grid’s Qualified Network Service Provider List.
Check both lists yourself, for the exact charger model and the exact software provider, before anyone signs a quote.
There is a longer-term point too. The 2027 rules are unknown, and you will own the chargers for many years. Choose chargers that use OCPP, the open protocol between a charger and its management software, so you can change software later without replacing the hardware. Our Connect Business software works with OCPP 1.6 and 2.0.1 chargers from any manufacturer, and OCPP chargers can move to it without being replaced.
What to do this month
- Find out who your utility is. Eversource and National Grid have different programs and different dates.
- Tell owners, and small associations, about 1 November. A charger used by one household, or one shared in a two-to-four-unit building, needs a complete Eversource application with Managed Charging enrollment by then.
- For a shared garage in Eversource territory: contact Eversource this week. Funding is reserved only by a Letter of Agreement executed and returned by 31 December.
- For a shared garage on a shared meter (National Grid): email the program team (EVnationalgrid@nationalgrid.com) this week to ask whether funding is still available for your building. Plan to have a signed Pre-Approval Offer Letter back before 31 December.
- Check MassEVIP for your building, and have your installer check the EPRI Vetted Products List for the charger model and the Qualified Network Service Provider List for the software.
- Do not start work before approval. Purchases and construction before approval can cost you the incentive.
- If you miss 2026, keep the paperwork ready. Site details, load information and quotes will still be useful under whatever 2027 brings.
Planning chargers for your building?
The 2026 deadlines are close, and the 2027 rules are not yet known. Either way, the chargers you choose will outlast both programs. If you are planning chargers or software for a condo or multifamily building, book a business demo and we will go through your plans with you.
This post describes what the utilities, MassDEP and the DPU publish. It is not legal or financial advice. Check current terms with your utility before you apply.
Sources
- Eversource, residential EV charger rebates (opens in a new tab) ()
- Eversource, EV Charger Managed Charging (opens in a new tab) ()
- Eversource, business EV charging rebates (opens in a new tab) ()
- National Grid, Multi-Unit Dwelling Programs (opens in a new tab) ()
- National Grid, Public/Workplace Programs (opens in a new tab) ()
- Massachusetts DPU, EV charging resources (opens in a new tab) ()
- Massachusetts DPU, 2026-01-16 (opens in a new tab) ()
- Massachusetts DPU, 2026-01-16 (opens in a new tab) ()
- MassDEP, MassEVIP multi-unit dwelling incentives (opens in a new tab) ()