Status as of 22 October 2026.

If your strata is an existing strata (plan deposited by 31 December 2023), has five or more lots and sits in Metro Vancouver, the Fraser Valley or the Capital Regional District, it must obtain an electrical planning report (EPR) by 31 December 2026. Stratas elsewhere in BC have until 31 December 2028. Once the report is in hand, or the deadline has passed, owners can formally ask the strata to approve EV charging at their parking stall. Council then has three months to decide, and it cannot refuse unreasonably.

Your council will use the report to answer every charging request that follows. Here is what the rules say.

Who needs an EPR, and by when

The deadlines are set in the Strata Property Regulation, section 5.8, and summarized on the Province’s EPR page:

Strata Deadline
Existing strata (plan deposited by 31 December 2023), 5+ lots, land wholly or partly in Metro Vancouver, Fraser Valley or Capital Regional District 31 December 2026
Existing strata, 5+ lots, everywhere else in BC 31 December 2028
New strata (plan deposited after 31 December 2023), 5+ lots 5 years after the strata plan is deposited
Fewer than 5 lots No EPR required

Islands reachable only by air or boat fall under the 2028 date. Phased stratas follow section 5.9.

What the report covers and who can write it

Under section 5.11, the report must include, for example:

  • the current capacity of the strata’s electrical system and its existing demands, including any EV charging;
  • current peak demand and spare capacity;
  • an estimate of the capacity needed for future demands, including EV charging the strata expects to install;
  • practical steps to reduce demand on the system, upgrades or modifications that could add capacity, and how much capacity each would free up.

If every strata lot is supplied by the utility separately, a shorter report is allowed (section 5.11(3)).

Who can prepare it (section 5.10): a professional engineer or professional licensee engineering registered with Engineers and Geoscientists BC, or an applied science technologist (AScT) or technician (CTech) registered with ASTTBC. For stratas where every building is a “Part 9” building under the building code, a journeyperson construction or industrial electrician can also prepare it.

To pay for it, the Province’s page describes two ways: include it in the operating budget passed by majority vote at the annual general meeting, or approve a contingency reserve fund expense by majority vote at an annual or special general meeting.

What changes for EV charging requests

The owner-request process is in sections 90.1 to 90.3 of the Strata Property Act and Part 5.1 of the Regulation. The EPR duty itself is section 94.1.

When owners can ask. For a strata that must get an EPR, owners can make a request from the earlier of two dates: the day the strata first obtains its EPR, or the EPR deadline (section 5.4). For stratas that do not need an EPR, including those with fewer than five lots, the date is 31 December 2026.

What a request must include (section 5.3): the owner’s details and strata lot, the proposed equipment and its location, the parking stall, and a qualified contractor’s description of the work with a cost and time estimate. The charger must carry the electrical safety label required by section 21 of the Electrical Safety Regulation (section 5.5).

Two conditions first. The owner must have the exclusive right to use the stall (section 90.2(2)(b)). If the work is a significant change in the use or appearance of common property, it also needs a majority vote at an annual or special general meeting (sections 90.2(1)(a) and 71). Plan that meeting inside the three-month window.

What council may weigh (section 90.2(3)):

  • whether the proposed charger is compatible with existing EV charging in the building, with charging the strata or other owners may install later, and with “any system the strata corporation uses, or plans to use, to manage electricity used by EV charging infrastructure”;
  • the capacity of the electrical system and its current and expected demands.

What council must do. The strata “must not unreasonably refuse” a request (section 90.2(4)) and must decide within three months (section 90.2(6) and Regulation section 5.6). It can attach reasonable written conditions, for example approving the equipment and contractor, or requiring the owner to modify or replace their charger if the strata later installs charging for all owners (section 90.2(5)). Unless agreed otherwise, the owner pays for the alteration (section 90.3).

Put together: the EPR tells council how much capacity exists, and the Act lets council ask whether each new charger fits a building-wide plan. A strata that has a plan before the first request arrives will find the three-month clock much easier to meet.

This section summarizes the legislation as published on BC Laws. It is not legal advice. Ask your strata lawyer or property manager how it applies to your bylaws.

Rebates: an EPR is now required for charger rebates

The CleanBC Go Electric Home and Workplace Charging Program, run by BC Hydro and FortisBC, changed its rules in its Program Guide dated 1 April 2026:

  • From 15 July 2026, a standalone multi-unit residential building (MURB) charger rebate requires an EV Ready plan, an EPR “as mandated for strata corporations with five or more units under the Strata Property Act,” or an opportunity assessment report from the CleanBC MURB Retrofit Program.
  • Standalone MURB charger rebate: up to 50% of eligible costs, to a maximum of $2,000 per charger. Buildings that already received the EV Ready infrastructure rebate get up to $1,400 per charger instead. Strata corporations are limited to $14,000 in charger rebates per fiscal year (April to March).
  • Owners applying alone: since 1 April 2026, an owner applying alone needs a consent form signed by council.
  • EV Ready plan rebate: up to 75% of eligible costs, to a maximum of $3,000. EV Ready infrastructure rebate: up to 50%, to a maximum of $600 per parking stall and $120,000 per building.
  • Networking is required for MURB charger rebates. The guide defines it as the ability to send and receive commands or messages remotely “to a central network accessible by building management representatives,” and adds: “Stations must remain networked for a minimum of two years.”
  • Open protocols are encouraged. Participants are “highly encouraged” to use a non-proprietary protocol such as OCPP or OpenADR.
  • Buildings must have five or more units and have been built by 31 August 2022. You need pre-approval before any work starts, and funding is first-come, first-served while it lasts. Some municipalities add top-ups.

The Go Electric BC page listed the program as open on 22 October 2026; confirm with BC Hydro or FortisBC before you apply.

Billing residents in Canada

If your strata plans to bill residents per kWh, Measurement Canada’s dispensation for non-commercial Level 1 and 2 chargers covers chargers reserved for “owners and renters living in multi-unit residential buildings.” It applies to chargers put into service before 1 January 2028, if the owner applies by 31 December 2027. From 1 January 2030, chargers in service must be approved and verified, or removed from service.

Where software fits

An EPR often shows capacity for some chargers, not unlimited ones. Software can help a strata work within it:

  • Load balancing lets several chargers share one circuit’s limited capacity without exceeding it. Whether it suits your building, and at what limit, is for the person preparing your EPR or your electrical engineer to decide.
  • Driver groups, for example residents, control who may charge.
  • Records for council: payments and sessions export to CSV, for accounting and for the annual budget.

Our Connect Business software does all three, and it works with OCPP 1.6 and 2.0.1 chargers from any manufacturer.

What to do before the year ends

  1. Check your deadline. Confirm your regional district and lot count against section 5.8.
  2. Book the qualified person now. Year-end calendars fill up.
  3. Ask the report to model EV charging properly: how many stalls, at what charging level, and with or without load sharing.
  4. Write a building-wide charging plan before requests arrive: who pays, which equipment, which software, how residents are billed.
  5. Prepare a request form that matches section 5.3, so owners send complete requests.
  6. Use the EPR for rebates. Apply for pre-approval before any purchase or installation.

Planning chargers for your strata?

If your council is turning an EPR into a charging plan, book a business demo and we will go through it with you.

Sources

  1. Province of B.C., 5 Jun 2026 (opens in a new tab) ()
  2. BC Laws, Strata Property Act Part 5, to 13 Oct 2026 (opens in a new tab) ()
  3. BC Laws, Strata Property Act Part 6, to 13 Oct 2026 (opens in a new tab) ()
  4. BC Laws, Strata Property Regulation 43/2000, to 20 Oct 2026 (opens in a new tab) ()
  5. CleanBC Go Electric, 1 Apr 2026 (opens in a new tab) ()
  6. Go Electric BC, MURB charging rebates (opens in a new tab) ()
  7. Measurement Canada, non-commercial dispensation, 16 Sep 2025 (opens in a new tab) ()